Back to asset register
Halcyon Spa Wing
BS 5839-1 L1Action requiredASSET-006 · Halcyon Spa Wing · Halcyon Hotels · design D-306
Installed
28 Dec 2014
Last serviced
5 Nov 2025
Devices
17
Replacement due
15
Replacement planning
15 device(s) at or near end of life- Optical Smoke · Ground floorOverdue
- Optical Smoke · First floorOverdue
- Optical Smoke · Plant roomOverdue
- Optical Smoke · ReceptionOverdue
- Optical Smoke · CorridorOverdue
- Optical Smoke · Store roomOverdue
- Optical Smoke · RoofOverdue
- Optical Smoke · Ground floorOverdue
- Heat Detector · First floorOverdue
- Heat Detector · Plant roomOverdue
- Heat Detector · ReceptionOverdue
- Sounder · RoofOverdue
- +3 more — see the device register below
Device register
17 installed devices| Make / model | |||||
|---|---|---|---|---|---|
| Optical Smoke | Apollo Orbis Optical | Ground floor | SN-D-306-OPTI-001 | 5 Nov 2025 | Overdue |
| Optical Smoke | Hochiki ESP Optical | First floor | SN-D-306-OPTI-002 | 5 Nov 2025 | Overdue |
| Optical Smoke | Gent S-Quad Optical | Plant room | SN-D-306-OPTI-003 | 5 Nov 2025 | Overdue |
| Optical Smoke | Apollo Orbis Optical | Reception | SN-D-306-OPTI-004 | 5 Nov 2025 | Overdue |
| Optical Smoke | Hochiki ESP Optical | Corridor | SN-D-306-OPTI-005 | 5 Nov 2025 | Overdue |
| Optical Smoke | Gent S-Quad Optical | Store room | SN-D-306-OPTI-006 | 5 Nov 2025 | Overdue |
| Optical Smoke | Apollo Orbis Optical | Roof | SN-D-306-OPTI-007 | 5 Nov 2025 | Overdue |
| Optical Smoke | Hochiki ESP Optical | Ground floor | SN-D-306-OPTI-008 | 5 Nov 2025 | Overdue |
| Heat Detector | Hochiki ESP Heat | First floor | SN-D-306-HEAT-001 | 5 Nov 2025 | Overdue |
| Heat Detector | Apollo Orbis Heat | Plant room | SN-D-306-HEAT-002 | 5 Nov 2025 | Overdue |
| Heat Detector | Hochiki ESP Heat | Reception | SN-D-306-HEAT-003 | 5 Nov 2025 | Overdue |
| Manual Call Point | C-TEC Call Point CP3 | Corridor | SN-D-306-MCP-001 | 5 Nov 2025 | OK |
| Manual Call Point | Apollo Orbis MCP | Store room | SN-D-306-MCP-002 | 5 Nov 2025 | OK |
| Sounder | Hochiki Banshee Sounder | Roof | SN-D-306-SOUN-001 | 5 Nov 2025 | Overdue |
| Sounder | C-TEC Hush Sounder | Ground floor | SN-D-306-SOUN-002 | 5 Nov 2025 | Overdue |
| Sounder | Hochiki Banshee Sounder | First floor | SN-D-306-SOUN-003 | 5 Nov 2025 | Overdue |
| Sounder | C-TEC Hush Sounder | Plant room | SN-D-306-SOUN-004 | 5 Nov 2025 | Overdue |
Service history
Service visit
Routine service — all devices tested.
5 Nov 2025 · James Taylor
Inspection
Visual inspection — no structural or occupancy changes affecting conformity.
6 Oct 2025 · James Taylor
Certificate
BS 5839-1 commissioning certificate issued.
28 Dec 2014 · Andy Griffey
Install
System commissioned and handed over (design D-306).
28 Dec 2014 · Andy Griffey