Back to jobs
Stoneworks weighbridge
InstallCommissioningJ-2016 · Stoneworks Manufacturing · Stoneworks Factory
Lifecycle
TypeInstall· locked once scheduled
- Created
- Scheduled
- In Progress
- Commissioning
- Complete
- Handed Over
Getting to site
Get directionsStoneworks Factory
Foundry Lane, Derby
DE1 3RT
How to get in
Contractor pass
Access hours
Mon–Fri, 8:00am–5:00pm
Parking
Street parking — pay & display nearby
Design package
No design package linked.
Device schedule
0 devicesNo device schedule available.
Commissioning checklist
BS 5839-1 Cl. 41 · 0/5 checkedSystem checks
- Control panel: mains and standby supply verified
- Cause & effect matrix verified against design
- All zones correctly mapped and annunciated
- Sounder sound pressure level ≥ 65 dB(A) throughout
- Fault and disablement indication tested
James Taylor is not recorded as a competent person, so cannot sign off commissioning. A competent person must sign it.
Defects (0 open)
BS 5839-1 Cl. 44.2 · severity drives the remediation windowNo defects raised on this job.
Raise a defect
As-built variations (0)
On-site deviations from the design · JOB-7No variations — installed as designed.
Material list
No material list (job has no linked quote).
Materials & stock
0 allocation(s)No stock allocated to this job yet.
Labour & profitability
From approved timesheets- Quoted value
- —
- Approved labour
- £0
- Margin (ex-materials)
- —
Competent-person attendance
No time logged against this job yet.
Site information
- Property
- Stoneworks Factory
- Address
- Foundry Lane, Derby
- Postcode
- DE1 3RT
- Building type
- Industrial
- Floors
- 2
- System category
- BS 5839-6 P1
Floor plans
- Ground floor· PDF · 22 May
- First floor· IMAGE · 16 May
Engineers & dates
AM
Alex MorganLeadPrimary
Completion
Mark the job complete to trigger handover documentation.
Acceptance certificate
BS 5839-1 Cl. 40.3 / Annex G.4 — required before handover.Not yet generated.
Available once the job is Complete.
Lifecycle audit
- Reconstructed from this job's current stage — recorded transitions start from the next change.
- In ProgressCommissioning24 May · Alex Morgan
- ScheduledIn Progress23 May · Alex Morgan
- CreatedScheduled22 May · Alex Morgan
- —Created21 May · Alex Morgan
Notes
- Control panel positioned; awaiting final containment.1 Jun · Alex Morgan
- Client walkthrough booked for end of week.29 May · Alex Morgan
- Zone plan reviewed against the device schedule.26 May · Alex Morgan
Issues & holds
No issues or holds.