Back to jobs

Northgate clubhouse

InstallCreated

J-2007 · Northgate Developments · Northgate Phase 2 Apartments

Lifecycle
Type
  1. Created
  2. Scheduled
  3. In Progress
  4. Commissioning
  5. Complete
  6. Handed Over
Getting to site
Get directions
Northgate Phase 2 Apartments
Northgate Way, Leeds
LS2 7QR
How to get in
Key holder on site
Access hours
Mon–Fri, 8:00am–5:00pm
Parking
On-site visitor parking
Site contact
James Bloggs
Call site contact
Northgate clubhouse
Design D-311 · 100% complete
Compliant
Device schedule
11 devices
DeviceQty
Optical Smoke4
Heat Detector2
Manual Call Point2
Sounder3
Commissioning checklist
BS 5839-1 Cl. 41 · 0/9 checked
System checks
  • Control panel: mains and standby supply verified
  • Cause & effect matrix verified against design
  • All zones correctly mapped and annunciated
  • Sounder sound pressure level ≥ 65 dB(A) throughout
  • Fault and disablement indication tested
Device checks
  • Optical Smoke — function test (×4)
  • Heat Detector — function test (×2)
  • Manual Call Point — function test (×2)
  • Sounder — function test (×3)

James Taylor is not recorded as a competent person, so cannot sign off commissioning. A competent person must sign it.

Defects (0 open)
BS 5839-1 Cl. 44.2 · severity drives the remediation window

No defects raised on this job.

Raise a defect

As-built variations (0)
On-site deviations from the design · JOB-7

No variations — installed as designed.

Material list
ItemQtyUnit £Line £
Apollo Orbis Optical4£42£168
Apollo Standard Base4£4£16
Generic Fixings Pack4£2£8
Hochiki ESP Heat2£30£60
C-TEC Call Point CP32£22£44
Hochiki Banshee Sounder3£28£84
Materials & stock
0 allocation(s)

No stock allocated to this job yet.

Labour & profitability
From approved timesheets
Quoted value
£16,800
Approved labour
£0
Margin (ex-materials)
£16,800
Competent-person attendance

No time logged against this job yet.

Site information
Property
Northgate Phase 2 Apartments
Address
Northgate Way, Leeds
Postcode
LS2 7QR
Building type
Residential
Floors
6
System category
BS 5839-6 LD2
Floor plans
  • Ground floor· PDF · 22 May
  • First floor· IMAGE · 16 May
  • Second floor· PDF · 10 May
View property →
Engineers & dates
BC
Beth CarterLeadPrimary
Completion

Mark the job complete to trigger handover documentation.

Acceptance certificate
BS 5839-1 Cl. 40.3 / Annex G.4 — required before handover.

Not yet generated.

Available once the job is Complete.

Lifecycle audit
  • Reconstructed from this job's current stage — recorded transitions start from the next change.
  • —Created
    23 May · Beth Carter
Notes
  • Control panel positioned; awaiting final containment.
    1 Jun · Beth Carter
  • Client walkthrough booked for end of week.
    29 May · Beth Carter
  • Zone plan reviewed against the device schedule.
    26 May · Beth Carter
Issues & holds